Proposal Description
Basic Assessment (BA) process for the new transmission line and switching station connecting the Kokerboom 4 WEF to the Eskom Helios MTS via the Khobab Substation.The site of the Kokerboom 4 WEF which the proposed transmission line will connect to will be located approximately 59 km north of Loeriesfontein, 85 km west of Brandvlei and 160 km south-east of Springbok in the Northern Cape. The transmission line will be connecting to the existing Khobab Substation which is connected to the Helios MTS which will feed into the existing national Eskom electricity
grid.
grid.
Post date
09/07/2021 - 16:34
Last modified
21/10/2023 - 13:14
Reports
HIA for the Kokerboom 4 Grid connection | Jayson Orton | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits