Eskom Holdings SOC Ltd, Limpopo Operating Unit (LOU) hereby notifying you that it intends to construct the powerline for the above-mentioned project. There is an existing line in the project area and some portion of the line is running parallel to the dam. The purpose of a new line is to move that part which is next to the dam to a new area. The powerline will include new 573m MV that will be connected from pole number VS219/24/20 and will be supplying a game farm on remainder of Portion 9 of Farm Zanddrift 94KR in the Modimolle Local Municipality of Waterberg District Municipality.
Post date
13/07/2021 - 21:13
Last modified
21/10/2023 - 13:15
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document |