CaseDetails
    Summary
    Case ID
    15763
    Case Status
    Heritage Authority(s)
    SAHRA
    NBKB
    Proposal Description
    The Kudu power station and 400KV lines were authorised for construction in 2017 and included the clearance of vegetation for the expansion of the substation, the development of the new road (over 4m wide) and the development of the structures and infrastructure for the transmission/distribution of electricity. The powerline corridor was authorised based on specific tower positions around the Orange river due to the high sensitivities.

    The proposed amendments to the EA are to the technological/design aspects of the powerline which crosses the orange river, BUT will remain within the previously authorised corridor and are as follow:
    Switch from 518 series to 540 series
    Reduce the two X 400kv lines to one
    Reduce the number of towers from 20 to 8
    Increase the individual footprint of each tower from 12m² to 17m²
    Repositioning of an existing tower on the south site of the substation

    The motivation for these changes are that they:
    Reduce the overall environmental impact on the area (fewer structures)
    No flashover caused during blowout as new line will be further from the 66kv line
    540 series allow for longer spans- fewer blowout issues
    Longer span allows for higher clearance over the river
    Overall improved reliability of the line- reduced risk.
    Author
    jenna.lavin
    Last modified
    21/10/2023 - 13:15
    Reports
    Heritage Reports linked to this Case
    HIA Letter of Exemption Heritage Screener: Kudu Power Station Jenna Lavin download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document