    Proposal Description
    This project is an Eskom Greenfield Electrification Project. The village Mareetsane Zones 2,7 & 8 falls under Stella CNC and under the Tswaing Local Municipality. It is part of the 2022/2023 Electrification Plan. The village zones consists of 166 new stands and 100% of them are occupied. The houses are of brick and Tin type. The village has no other services installed and with electricity to be installed by Eskom.

    The aim of this project is the electrification of 166 new stands at Mareetsane Zones 2,7 & 8. Electrical reticulation, i.e. conductor network, will be provided which can deliver 1.02kVA per stand.
    Author
    Oarabile.Mabula
    Last modified
    21/10/2023 - 13:25
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Decision Access Document