Proposal Description
The proposed project is located ± 34kms to the southeast of Emalahleni and ± 24km north of Bethal. The project is proposed on Komati Power Station 56-IS Remainder; Goedehoop 46-IS R/3, Portions 8/3, 2, Re, 4; Kleinfontein 49-IS Portions 10/1, RE/4, 12/4, 8/4; in the jurisdiction of Steve Tshwete Local Municipality (Nkangala DM) and Schoonvlei 52-IS Portion 2, Middelkraal 50-IS 8/3, R/3 in Govan Mbeki Local Municipality (Gert Sibande DM), Mpumalanga Province.
The proposed Kudu-Elders 132kV power line is approximately 26km in length. The existing Kudu Substation is situated on the property of the Komati Power Station.
The proposed Kudu-Elders 132kV power line is approximately 26km in length. The existing Kudu Substation is situated on the property of the Komati Power Station.
Post date
11/09/2022 - 13:53
Last modified
21/10/2023 - 13:27
Reports
HIA Phase 1 | HIA Kudu Elders power line and Elders substation | Jaco van der Walt | download, download |
Official Use
Official
Case Officers
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |