ABO Wind renewable energies (Pty) Ltd proposes the construction and operation of a grid connection to connect the Springhaas solar PV facilities located south-west of Dealesville in the Free State Province to add new capacity to the national electricity grid. In order for the Springhaas Solar PV facilities to evacuate the generated solar power to the national grid, a connection must be established between the solar PV facilities and the existing Eskom 400kV lines, namely the Beta/Delphi and Beta/Hydra lines located to the east and west of the solar PV facilities respectively.
Collector Substation A will have a capacity of up to 400kV and is located on Remainder of Farm Corneliasdal, near Dealesville, Bloemfontein, Free State Province.
Collector Substation A will have a capacity of up to 400kV and is located on Remainder of Farm Corneliasdal, near Dealesville, Bloemfontein, Free State Province.
Post date
19/09/2022 - 09:05
Last modified
23/10/2023 - 17:59
Reports
Heritage Impact Assessment Specialist Reports | Springhaas Collector Substation A Heritage Impact Assessment | Jayson Orton | download | |
PIA Desktop | Springhaas Collector Substation A Palaeontological Impact Assessment | Marion Bamford | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |
Final Decision | Access Document |