CaseDetails
    Summary
    Case ID
    18237
    Case Status
    Heritage Authority(s)
    SAHRA
    HFS
    Proposal Description
    ABO Wind renewable energies (Pty) Ltd proposes the construction and operation of a grid connection to connect the Springhaas solar PV facilities located south-west of Dealesville in the Free State Province to add new capacity to the national electricity grid. In order for the Springhaas Solar PV facilities to evacuate the generated solar power to the national grid, a connection must be established between the solar PV facilities and the existing Eskom 400kV lines, namely the Beta/Delphi and Beta/Hydra lines located to the east and west of the solar PV facilities respectively.

    Collector Substation A will have a capacity of up to 400kV and is located on Remainder of Farm Corneliasdal, near Dealesville, Bloemfontein, Free State Province.
    Author
    kate.flood
    Last modified
    23/10/2023 - 17:59
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports Springhaas Collector Substation A Heritage Impact Assessment Jayson Orton download
    PIA Desktop Springhaas Collector Substation A Palaeontological Impact Assessment Marion Bamford download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Decision Access Document
      Final Decision Access Document