CaseDetails
Summary
Case ID
18896
Case Status
Official Reference
20328
Proposal Description
Construction is underway for the authorised 132 kV powerline between the existing Nhlavuko substation and Tshebela/Rampheri new substation. Three deviations to the authorised route are being applied for. The project is located in the south of Polokwane Municipal area, Capricorn District Municipality, Limpopo Province.
Post date
09/12/2022 - 09:17
Last modified
23/10/2023 - 17:59
Reports
HIA Phase 1 | Eskom NT HIA | Nikki Mann | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|