CaseDetails
    Summary
    Case ID
    18927
    Case Status
    Heritage Authority(s)
    SAHRA
    LIHRA
    Official Reference

    20360

    Proposal Description
    Eskom Holdings SOC Ltd (the applicant) appointed Setala Environmental (Pty) Ltd as the independent environmental assessment practitioner (EAP) to undertake the Environmental Impact Assessment (EIA) for a proposed electricity strengthening project.

    The National Department of Environmental Affais (DEA) issued Environmental Authorisation for the construction of a 132kV power line from the existing Paradise Substation to the proposed Fondwe Substation, on 05 October 2015, (DEA Ref 14/12/16/3/3/1/1337) and a subsequent amendment authorised on 25 March 2019. DEA Ref 14/12/16/3/3/1/1337/AM3.

    Following on the above, an application for authorisation for deviation of a section of the above-mentioned power line is submitted to the National Department of Forestry, Fisheries and the Environment (DFFE), in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998) (NEMA) and the Environmental Impact Assessment (EIA) Regulations of 2014, as amended.
    Author
    ria.pretorius
    Last modified
    21/10/2023 - 13:30
    Reports
    Heritage Reports linked to this Case
    HIA Paradise-Fondwe deviation line Trust Mlilo download
    PIA Desktop PIA desktop report Marion Bamford download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type