CaseDetails
Summary
Case ID
19156
Case Status
Proposal Description
The proposed development of the Springhaas to Artemis grid connection. A powerline of up to 275kV in capacity to connect the proposed Springhaas Solar PV facilities to the proposed Artemis substation to allow power to be evacuated to the national grid.
Post date
31/01/2023 - 10:32
Last modified
23/10/2023 - 18:00
Reports
HIA Phase 2 | Springhaas to Artemis Line 1 HIA | Jayson Orton | download | |
PIA Phase 1 | Springhaas to Artemis Line 1 PIA | Marion Bamford | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |