Scope of Work
▪ Construct new 44km of 3-ph 33kV MV Hare overhead line from Planted pole
(outside Mmabatho Main Sub) until pole no: ACS-MAL 380.
▪ Lay ±100m of 300mm² 3C XLPE Al cable to cross 88kV Lines and 33kV Line.
▪ Install 1 x Auto-reclosers in accordance to D-DT-1829 at newly installed pole
before pole no: ACS-MAL 380.
▪ Create a normal open (N/O) at pole no: ACS-MAL 379.
▪ Create a normal open (N/O) at pole no: ACS-MAL 380.
▪ Close the span/connect to the Gantry at Mmabatho Main Substation.
▪ Stencil new feeder and re-stencil entire ACS-MAL feeder with new name.
▪ Construct new 44km of 3-ph 33kV MV Hare overhead line from Planted pole
(outside Mmabatho Main Sub) until pole no: ACS-MAL 380.
▪ Lay ±100m of 300mm² 3C XLPE Al cable to cross 88kV Lines and 33kV Line.
▪ Install 1 x Auto-reclosers in accordance to D-DT-1829 at newly installed pole
before pole no: ACS-MAL 380.
▪ Create a normal open (N/O) at pole no: ACS-MAL 379.
▪ Create a normal open (N/O) at pole no: ACS-MAL 380.
▪ Close the span/connect to the Gantry at Mmabatho Main Substation.
▪ Stencil new feeder and re-stencil entire ACS-MAL feeder with new name.