CaseDetails
    Summary
    Case ID
    19224
    Case Status
    Heritage Authority(s)
    SAHRA
    Proposal Description
    Scope of Work

    ▪ Construct new 44km of 3-ph 33kV MV Hare overhead line from Planted pole
    (outside Mmabatho Main Sub) until pole no: ACS-MAL 380.
    ▪ Lay ±100m of 300mm² 3C XLPE Al cable to cross 88kV Lines and 33kV Line.
    ▪ Install 1 x Auto-reclosers in accordance to D-DT-1829 at newly installed pole
    before pole no: ACS-MAL 380.
    ▪ Create a normal open (N/O) at pole no: ACS-MAL 379.
    ▪ Create a normal open (N/O) at pole no: ACS-MAL 380.
    ▪ Close the span/connect to the Gantry at Mmabatho Main Substation.
    ▪ Stencil new feeder and re-stencil entire ACS-MAL feeder with new name.