CaseDetails
Summary
Case ID
19570
Case Status
Proposal Description
ENERTRAG South Africa (Pty) Ltd (ESA) (the Developer) is proposing the development of a Camden Renewable Energy Complex comprising various projects within the vicinity of the Camden Power Station in Mpumalanga. The Complex consists of eight distinct projects referred to as:
- Camden I Wind Energy Facility (WEF) (up to 200MW): Subject to a Scoping and Environmental Impact Reporting (S&EIR) process (DFFE Ref: 14/12/16/3/3/2/2137);
Camden I Wind Grid Connection (up to 132kV): Subject to a Basic Assessment (BA) process;
Camden Grid Connection and Collector substation (up to 400kV): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2134);
- Camden I Solar Energy Facility (SEF) (up to 100MW): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2136);
- Camden I Solar Grid Connection (up to 132kV): Subject to a BA process; (this report & application)
- Camden II WEF (up to 200MW): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2135);
- Camden II WEF up to 132kV Grid Connection: Subject to a BA process; and
- Camden Green Hydrogen and Ammonia Facility and associated infrastructure: Subject to a S&EIR process (MDARDLEA Ref: 1/3/1/16/1G-242).
The Complex (except for the Green Hydrogen and Ammonia project) is being developed in the context of the Department of Mineral Resources and Energy’s (DMRE Integrated Resource Plan, and the Renewable Energy Independent Power Producer Procurement Programme (REIPPP).
The proposed Camden I SEF will be connected to the nearby Camden Collector substation (which in turn will connect to the Camden Power Station), through an up to 132kV powerline (either single or double circuit) between the grid connection substation portion (immediately adjacent the Camden I Solar PV on-site IPP substation portion) and that of the Camden Collector substation.
The focus of this Application is the proposed Camden up to 132kV Grid Connection powerline and associated infrastructure.
The proposed project entails the construction of an up to 132kV Grid connection overhead powerline including associated infrastructure, from the Camden I Solar PV Facility to the nearby Camden Collector substation (which in turn will connect to the Camden Power Station). The powerline will be approximately 5km in length, depending on the authorized location of the collector substation.
The onsite grid connection substation will consist of high voltage substation yard to allow for multiple (up to) 132kV feeder bays and transformers, control building, telecommunication infrastructure, access roads, etc. The area for the onsite substation will be up to 1.5ha. The up to 132kV powerline and substation will have a 500m corridor (250m either side of the centre line, and 250m around the entire perimeter of the proposed substation sites), to allow for micro-siting and avoidance of sensitive features where possible. This corridor, as opposed to the line routing, is proposed for authorisation. This application includes the necessary up to 132kV voltage electrical components required for connection at the Collector Substation (i.e. the termination works).
The proposed project will comprise the following key components:
- The grid connection substation (adjacent the IPP substation), consisting of a high voltage substation yard to allow for multiple (up to) 132kV feeder bays and transformers, control building, telecommunication infrastructure, access roads, lighting and fencing;
- Construction of an up to 132kV power line (either single or double circuit) between the grid connection substation portion and that of the Camden Collector substation; and
- Termination works, comprising the necessary up to 132kV voltage electrical components required for connection at and into the Collector Substation.
- Existing or new access and service roads (utilising existing roads where possible, with new roads developed where there are no existing roads to be utilised).
- Camden I Wind Energy Facility (WEF) (up to 200MW): Subject to a Scoping and Environmental Impact Reporting (S&EIR) process (DFFE Ref: 14/12/16/3/3/2/2137);
Camden I Wind Grid Connection (up to 132kV): Subject to a Basic Assessment (BA) process;
Camden Grid Connection and Collector substation (up to 400kV): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2134);
- Camden I Solar Energy Facility (SEF) (up to 100MW): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2136);
- Camden I Solar Grid Connection (up to 132kV): Subject to a BA process; (this report & application)
- Camden II WEF (up to 200MW): Subject to a S&EIR process (DFFE Ref: 14/12/16/3/3/2/2135);
- Camden II WEF up to 132kV Grid Connection: Subject to a BA process; and
- Camden Green Hydrogen and Ammonia Facility and associated infrastructure: Subject to a S&EIR process (MDARDLEA Ref: 1/3/1/16/1G-242).
The Complex (except for the Green Hydrogen and Ammonia project) is being developed in the context of the Department of Mineral Resources and Energy’s (DMRE Integrated Resource Plan, and the Renewable Energy Independent Power Producer Procurement Programme (REIPPP).
The proposed Camden I SEF will be connected to the nearby Camden Collector substation (which in turn will connect to the Camden Power Station), through an up to 132kV powerline (either single or double circuit) between the grid connection substation portion (immediately adjacent the Camden I Solar PV on-site IPP substation portion) and that of the Camden Collector substation.
The focus of this Application is the proposed Camden up to 132kV Grid Connection powerline and associated infrastructure.
The proposed project entails the construction of an up to 132kV Grid connection overhead powerline including associated infrastructure, from the Camden I Solar PV Facility to the nearby Camden Collector substation (which in turn will connect to the Camden Power Station). The powerline will be approximately 5km in length, depending on the authorized location of the collector substation.
The onsite grid connection substation will consist of high voltage substation yard to allow for multiple (up to) 132kV feeder bays and transformers, control building, telecommunication infrastructure, access roads, etc. The area for the onsite substation will be up to 1.5ha. The up to 132kV powerline and substation will have a 500m corridor (250m either side of the centre line, and 250m around the entire perimeter of the proposed substation sites), to allow for micro-siting and avoidance of sensitive features where possible. This corridor, as opposed to the line routing, is proposed for authorisation. This application includes the necessary up to 132kV voltage electrical components required for connection at the Collector Substation (i.e. the termination works).
The proposed project will comprise the following key components:
- The grid connection substation (adjacent the IPP substation), consisting of a high voltage substation yard to allow for multiple (up to) 132kV feeder bays and transformers, control building, telecommunication infrastructure, access roads, lighting and fencing;
- Construction of an up to 132kV power line (either single or double circuit) between the grid connection substation portion and that of the Camden Collector substation; and
- Termination works, comprising the necessary up to 132kV voltage electrical components required for connection at and into the Collector Substation.
- Existing or new access and service roads (utilising existing roads where possible, with new roads developed where there are no existing roads to be utilised).
Post date
03/04/2023 - 18:57
Last modified
23/10/2023 - 18:00
Reports
HIA Phase 1 | Heritage Register Appendix 1 | Jaco van der Walt | download | |
Heritage Impact Assessment Specialist Reports | HIA - Camden I SEF 132kV Grid connection | Jaco van der Walt | download | |
PIA Phase 2 | PIA - Camden I SEF 132kV Grid Connection | Marion Bamford | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |