CaseDetails
Summary
Case ID
19605
Case Status
Proposal Description
The project entails construction of a new powerline parallel to the existing underground cable. Plant a 12m pole outside of Cooks Lake switching station. Use 12m three pole structures to cross the water resources with a span of 194m. Build an 11kV overhead power line of approximately 1km towards Danville Switching Station. Terminate with an 11kV cable on the terminal pole towards Danville Switching Station.
Post date
13/04/2023 - 10:15
Last modified
21/10/2023 - 13:35