    Proposal Description
    The primary rationale for the proposed inclusion to the authorised Solar Power Plant (SPP) is to
    increase the proposed footprint of the facility to enable the authorised generation capacity of the SPP
    and ultimately add new generation capacity from renewable energy to the national electricity mix and
    to aid in achieving the goal of 42% share of all new installed generating capacity being derived from
    renewable energy forms, as targeted by DMRE (Integrated Resource Plan Update 2010-2030). The IRP
    also identifies the preferred generation technologies required to meet the expected demand growth
    up to 2030 and incorporates government objectives including affordable electricity, reduced
    greenhouse gas (GHG) emissions, reduced water consumption, diversified electricity generation
    sources and localisation and regional development. In terms of the Integrated Resource Plan Update
    (2019 IRP Update, 2010-2030), over the short term (of the next two or three years), clear guidelines
    arose; namely to continue with the current renewable bid programme with additional annual rounds
    of 1000 MW PV, with approximately 8.4GW of the renewable energy capacity planned to be installed
    from PV technologies over the next twenty years.
    Author
    carli.steenkamp
    Last modified
    21/10/2023 - 13:36
    Reports
    Heritage Reports linked to this Case
    HIA download, download
    PIA download, download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document