Proposal Description
The activity entails the development of grid
connection infrastructure which consists of 132kV
single/double-circuit overhead power line with the
associated infrastructure on Remaining Extent of
Farm Paradys No. 137. A 400m wide (including
temporary working area), on average and 9.2km
long grid connection corridor is being assessed for
the placement of the power line route. The power
line is proposed to connect into the existing Eskom
Mercury Substation. A service road associated with
the powerline is also proposed to be developed.
The grid connection corridor is approximately 22km
north-west from the town of Viljoenskroon and falls
within the Moqhaka Local Municipality of the Fezile
Dabi District Municipality, Free State Province
connection infrastructure which consists of 132kV
single/double-circuit overhead power line with the
associated infrastructure on Remaining Extent of
Farm Paradys No. 137. A 400m wide (including
temporary working area), on average and 9.2km
long grid connection corridor is being assessed for
the placement of the power line route. The power
line is proposed to connect into the existing Eskom
Mercury Substation. A service road associated with
the powerline is also proposed to be developed.
The grid connection corridor is approximately 22km
north-west from the town of Viljoenskroon and falls
within the Moqhaka Local Municipality of the Fezile
Dabi District Municipality, Free State Province
Post date
03/08/2023 - 14:24
Last modified
16/11/2023 - 10:04
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Interim Comment | Access Document |