    Proposal Description
    Sibanye-Stillwater is planning to extend the life of mine at K4 Shaft with 30 years and is planning to construct additional infrastructure around the current Waste Rock Dump (WRD) footprint to contain the dirty water run-off from the WRD. The additional infrastructure includes the construction of a V-drain catchment berm, new Pollution Control Dam (PCD), a pipeline from the PCD to the shaft and an emergency spillway.
    Author
    lenaldi.gorgens
    Last modified
    10/12/2024 - 14:48
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports K4 Shaft PCD HIA Jaco van der Walt download
    Official
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document
      Interim Comment Access Document