CaseReference
Applicable legislation
34(1)
Decision Date
Committee
Decision Status
Case Decision

The permit application in respect of the above, received on the 29 June 2022 reviewed by the KwaZulu-Natal Amafa and Research Institute (The Institute) on the 13 July 2022.  
Please be advised as follows:

It was noted that the front façade will be retained, however the roof design has changed. As discussed please revise the roof front façade, if possible can the roof front eave be restored and the timber deck proposal be setback. Or provide an alternative design which is going to distinguish original design from the new proposed design. 
Provide internal photographs of all areas to be altered.

Written responses/requests for reconsideration of the application or consideration of new information must be loaded to the case on Sahris (email [email protected]) within 30 days of the date of this letter or any requirements/decisions contained herein will be considered final.  Extensions of this time frame can be requested upon receipt of motivation.
Required additional information or revised drawings must be submitted within six months from the date of this letter or the application will lapse and a new application will be required.
THIS LETTER DOES NOT CONSTITUTE FORMAL APPROVAL OF THE PROPOSAL SUBMITTED TO THE INSTITUTE.  UNAUTHORISED WORK CARRIED OUT ON THE ABOVE SITE WILL BE IN CONTRAVENTION OF THE KWAZULU-NATAL AMAFA AND RESEARCH INSTITUTE ACT (5 of 2018).