CaseReference
Applicable legislation
38(8)
Decision Date
Committee
Decision Status
Case Decision
Interim Comment
SAHRA notes the submitted Palaeontological Assessment, however, requires clarity on the EMPr update process as it has been 21 months since the original submission of documents to the case. It is noted that mitigation work as recommended in the 2009 AIA has been conducted (see SAHRIS Case ID 14221 https://sahris.sahra.org.za/cases/oena-mine-archaeological-mitigation).
Further comments will be issued upon receipt of the above information.
Case 13224 - Interim Comment_0.pdf (96.77 KB)