Applicable legislation
35
Decision Date
Decision Status
Case Decision

The following gaps are evident in the CMP as per the SAHRA Guidelines for Site Management Plans:

4.4. There is no discussion regarding stakeholders linked to the site, meetings or stakeholder input into the CMP;
4.8 No SWOT analysis has been conducted;
4.10 Visitor Management must be expanded upon such as entrance fee, carrying capacity, and safety of visitors;
4.15 Monitoring and evaluation principles to be discussed including a monitoring schedule and monitoring reports;
4.16 No discussion regarding implementation plan and reporting;
Additionally, the site is not a Provincial Heritage Site.

Please amend the above in order for the destruction permit to be processed.