Applicable legislation
35(3)
38(8)
Decision Date
Decision Status
Case Decision

The SAHRA DAU requires the monitoring by a heritage specialist during the initial excavations in the areas around EXIGO-BSP-IA03, EXIGO-BSP-IA04, EXIGO-BSP-IA05 and EXIGO-BSP-IA07. A monitoring report must be submitted upon the completion of the construction phase in these areas. 

Once the monitoring report is submitted, and no cultural material is identified in these areas, after SAHRA has approved the monitoring report, then the CFP can be undertaken by the ECO.