CaseDetails
Summary
Case ID
23288
Case Status
Proposal Description
The Belvoir Aggregate III Mining Permit application study site directly overlaps the existing Belvoir Quarry site (quarries I and II), with a marginal reduction in size, from 4.9209ha to 4.9016ha. A Mining Permit for the quarry was issued on 11 November 2022, but the permit expired on 26 February 2024. Civil & General Contractors is, therefore, reapplying for a Mining Permit to continue work at the site.
Post date
12/08/2024 - 06:09
Last modified
12/08/2024 - 06:09
Reports
AIA Desktop | AIA(LOR)-Belvoir Aggregate Quarry III, Komani, EMLM, EC | Karen Van Ryneveld | download | |
PIA Desktop | PIA(D)-Belvoir Aggregate Quarry III, Komani, EMLM, EC | Elize Butler | download |