CaseDetails
Summary
Case ID
24678
Case Status
Proposal Description
Eskom Holdings SOC Ltd, Limpopo Operating Unit (LOU) intends to construct the power line for the above-mentioned project. The power line will be more than 300m MV, which will T-off from the existing power line in pole number (refer to the Span plan sheets and the Pegging Coordinates for more information). The project is situated at Shiviti village, at Greater Giyani Municipality under Mopani District.
Environmental Screening of the power line route was conducted during pegging of the power line route by Survey team and site verification done by Environmental Practitioner which lead to the generation of the servitude planning documents [Distribution Environmental Screening Document (DESD), Wayleave, Span plan and Pegging coordinates attached for your reference]. Heritage resources such as properly fenced off grave yards were not observed on site, see 6.3 of the DESD. The project is within the residential area and also runs at the edge of the village in the open area with minimum vegetation on the existing Eskom power line servitude that is already disturbed by current land use activities such as the existing roads, existing power line, houses and Property boundary fence. Given the observation that the area is already disturbed, Eskom LOU here by notifies SAHRA of the proposed construction of the power line which is more than 300M in length. However, should any of the heritage resources, including graves or human remains be encountered or discovered during construction, Eskom shall immediately cease construction, inform SAHRA office, other relevant Department and as soon as possible contract a professional archaeologist to inspect the findings and conduct investigation as prescribed by the Act
Province(s): Limpopo
Environmental Screening of the power line route was conducted during pegging of the power line route by Survey team and site verification done by Environmental Practitioner which lead to the generation of the servitude planning documents [Distribution Environmental Screening Document (DESD), Wayleave, Span plan and Pegging coordinates attached for your reference]. Heritage resources such as properly fenced off grave yards were not observed on site, see 6.3 of the DESD. The project is within the residential area and also runs at the edge of the village in the open area with minimum vegetation on the existing Eskom power line servitude that is already disturbed by current land use activities such as the existing roads, existing power line, houses and Property boundary fence. Given the observation that the area is already disturbed, Eskom LOU here by notifies SAHRA of the proposed construction of the power line which is more than 300M in length. However, should any of the heritage resources, including graves or human remains be encountered or discovered during construction, Eskom shall immediately cease construction, inform SAHRA office, other relevant Department and as soon as possible contract a professional archaeologist to inspect the findings and conduct investigation as prescribed by the Act
Province(s): Limpopo
Post date
04/03/2025 - 14:10
Last modified
28/03/2025 - 15:34
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document |