CaseDetails
    Summary
    Case ID
    24816
    Heritage Authority(s)
    SAHRA
    HFS
    Proposal Description
    The Applicant, Mohau Solar PV (Pty) Ltd, is proposing the construction of a solar photovoltaic (PV) facility (Mohau 2 Solar PV) located on the Farm Montesfield No. 431 and Portion 2 of the Farm Montesfield No. 266, approximately 6.5 km south-east of the town of Reddersburg in the Free State Province.

    The solar PV facility will comprise several arrays of PV panels and associated infrastructure and will have a contracted capacity of up to 410 MW. The development area is situated within the Kopanong Local Municipality area and greater Xhariep District Municipality.

    Five (05) additional solar PV facilities (Mohau 1 Solar PV, Mohau 3 Solar PV, Mohau 4 Solar PV, Mohau 5 Solar PV and Mohau 6 Solar PV) are concurrently being considered on the adjacent properties and are assessed through separate Scoping and Environmental Impact Assessment (S&EIA) processes.

    The proposed Mohau 2 Solar PV will cover approximately 720ha (assessed within a 723ha area) and will include the following infrastructure:
    • PV modules and mounting structures
    • Inverters and transformers
    • Battery Energy Storage System (BESS)
    • Site and internal access roads (between 6 m and 8 m wide)
    • Operation and Maintenance buildings including a gate house, ablution facilities, security building, control centre, offices, warehouses and workshops for storage and maintenance.
    • Construction Camps
    • Temporary and permanent laydown area
    • For health, safety and security reasons, the facility will be required to be fenced off from the surrounding farms.
    • Facility grid connection infrastructure, including:
    o 132kV on-site facility substations
    o Collector/switching stations
    o Internal cabling or power lines between the project components and the onsite facility substations
    o Proposed new Eskom Main Transmission Substation (MTS).
    o 132kV Overhead Line (OHL) interconnecting the proposed Eskom Switching station to the proposed Eskom MTS.
    o Loop in Loop out 400 kV OHL connection onto existing Eskom 400 kV OHL.

    Province(s): Free State
    Author
    Christia.vandyk
    Last modified
    28/03/2025 - 15:14
    Reports
    Heritage Reports linked to this Case
    Mohau 2 Heritage and Paleo Scoping Report download, download
    Official
    Case Officers
      Location
      Location