CaseDetails
Summary
Case ID
24892
Case Status
Proposal Description
Broadlands Solar PV1 (Pty) Ltd, is proposing the construction of a Photovoltaic (PV) Solar Energy Facility, Battery Energy Storage System (BESS) facility, and ancillary / associated infrastructure, including electrical grid infrastructure (herein referred to as Broadlands Solar PV1 Facility). The Solar PV Facility will comprise several arrays of PV panels and associated infrastructure and will have a contracted capacity of up to 240 MWAC. The town of Polokwane is located approximately 21 km north-east of the proposed development the Limpopo Province.
The proposed Broadlands Solar PV1 Facility will cover approximately 791 ha and will include the following infrastructure:
• PV modules and mounting structures.
• Inverters and transformers.
• Battery Energy Storage System (BESS).
• Perimeter, access and internal roads (between 6 m and 8 m wide).
• Supporting infrastructure such as operations and maintenance building/office, switch gear and relay room, staff lockers and changing room, security control, and offices.
• Temporary and permanent laydown areas.
• For health, safety and security reasons, the facility will be required to be fenced off from the surrounding farms.
• Facility grid connection infrastructure, including:
o Underground or overhead cabling between project components of up to 132 kV.
o An on-site IPP facility substation and switching station of up to 132kV.
o Single / double circuit overhead power lines of up 132 kV linking the proposed facility substation / Eskom switching station to the offsite Main Transmission Substation (MTS) . Two alternative grid connection corridors of up to 600 m wide and up to 12 km long have been identified for assessment.
The proposed Broadlands Solar PV1 Facility is undergoing a Scoping and Environmental Impact Assessment (S&EIA) process.
Province(s): Limpopo
The proposed Broadlands Solar PV1 Facility will cover approximately 791 ha and will include the following infrastructure:
• PV modules and mounting structures.
• Inverters and transformers.
• Battery Energy Storage System (BESS).
• Perimeter, access and internal roads (between 6 m and 8 m wide).
• Supporting infrastructure such as operations and maintenance building/office, switch gear and relay room, staff lockers and changing room, security control, and offices.
• Temporary and permanent laydown areas.
• For health, safety and security reasons, the facility will be required to be fenced off from the surrounding farms.
• Facility grid connection infrastructure, including:
o Underground or overhead cabling between project components of up to 132 kV.
o An on-site IPP facility substation and switching station of up to 132kV.
o Single / double circuit overhead power lines of up 132 kV linking the proposed facility substation / Eskom switching station to the offsite Main Transmission Substation (MTS) . Two alternative grid connection corridors of up to 600 m wide and up to 12 km long have been identified for assessment.
The proposed Broadlands Solar PV1 Facility is undergoing a Scoping and Environmental Impact Assessment (S&EIA) process.
Province(s): Limpopo
Post date
02/04/2025 - 10:45
Last modified
07/04/2025 - 09:39
Official Use
Official
Case Officers