CaseDetails
Summary
Case ID
24932
Case Status
Proposal Description
The proposed 2nd Aurora-Juno 400kV powerline commences at the existing Aurora NTCSA substation, situated approximately 20 km east of Saldanha Bay, within the Saldanha Bay Municipality in the West Coast District of the Western Cape. This powerline route extends for 165 km in a northerly direction, traversing through the Bergriver and Cederberg Municipalities. It ultimately connects to the existing Juno NTCSA substation, located roughly 8 km northwest of Vredendal within the Matzikama Municipality in the West Coast District of the Western Cape.
Province(s): Western Cape
Province(s): Western Cape
Post date
08/04/2025 - 11:52
Last modified
08/04/2025 - 11:52