CaseDetails
    Summary
    Case ID
    25115
    Case Status
    Heritage Authority(s)
    ECPHRA
    Proposal Description
    The proposed project entails the construction of a 13km 3-Phase link line from Gatyana substation to the existing Gatyana-Idutywa line and terminate at Idutywa-Willowvale using a Hare conductor. The purpose is to strengthen network of Mbashe Local Municipality, the powerline traverses the following villages Mboya and Mfezane. The activity consists of excavation, planting of new pole structures and string the conductor.
    Author
    Nosicelo Sinje
    Last modified
    11/05/2025 - 19:43
    Official
    Case Officers
      Location
      Location