    Proposal Description
    The contract entails the construction, supply, installation, commissioning, and training of staff for the construction of
    a wastewater treatment plant.
    The requirement is supply, installation, commissioning, and training for a wastewater treatment plant (package plant) that
    can treat 300 m3/day or 12,5 m3/hour. Therefore, this tender enquiry is for:
    a) The construction, supply, and installation of a 300 m3/day wastewater treatment plant (package plant).
    b) The connection of the plant to the existing infrastructure within the Robben Island site.
    c) The commissioning of the facility, including a six-month trial operation period to demonstrate operational reliability,
    as well as the training of the Employer’s staff in the operation and maintenance of the facility.
    Inventory Reference