CaseDetails
Summary
Case ID
20310
Case Status
Official Reference
Case No: SAH23/21830 and 23/033
Proposal Description
The Applicant commenced with the construction of the following infrastructure and is approximately 1.43 ha in extent:
• The construction of a building (wedding venue), including the laying of the foundations and installation of the roof and columns of the steel structure (350 m2).
• Amphitheatre (90% complete).
• Platform (150 m2) has been cleared for construction / storage containers.
• Lemon tree orchard – area has been cleared.
The development will consist of the following components:
Wedding Venue and Associated Infrastructure:
• Entrance foyer
• Reception venue
• Restaurant
• Kitchen
• Office space
• Ablutions
• Coats room
• Generator yard
• Lemon tree orchard
• Yard and courtyard
• Entrance circle and access road
• Parking
• Platform area for construction materials and storage containers
Amphitheatre:
• Platform area
• Concrete steps
Building Plan approval for the following has been issued by the Municipality:
• 650 m2 wedding venue.
• 8 x hotel rooms.
• 5 x chalets (150 m2 each).
• Staff housing / accommodation (250 m2).
• The construction of a building (wedding venue), including the laying of the foundations and installation of the roof and columns of the steel structure (350 m2).
• Amphitheatre (90% complete).
• Platform (150 m2) has been cleared for construction / storage containers.
• Lemon tree orchard – area has been cleared.
The development will consist of the following components:
Wedding Venue and Associated Infrastructure:
• Entrance foyer
• Reception venue
• Restaurant
• Kitchen
• Office space
• Ablutions
• Coats room
• Generator yard
• Lemon tree orchard
• Yard and courtyard
• Entrance circle and access road
• Parking
• Platform area for construction materials and storage containers
Amphitheatre:
• Platform area
• Concrete steps
Building Plan approval for the following has been issued by the Municipality:
• 650 m2 wedding venue.
• 8 x hotel rooms.
• 5 x chalets (150 m2 each).
• Staff housing / accommodation (250 m2).
Post date
07/07/2023 - 11:07
Last modified
23/10/2023 - 18:00
Reports
HIA Phase 1 | McLuckie HIA | Gary Trower | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Interim Comment | Access Document | |
Letter of Advice | Access Document |